This package includes the following parts:

JUNKERJucam 5000/50

KSS Demand | l/min | ||
Grinding Burn | |||
Energy | kWh | ||
Q´w | mm³/s | ||
Grinding wheel wear |
Reduction of coolant | 200 l/min | 113 l/min |
Problem: High flow rate led to shutdowns because of the overflow protection.
- Replacement of slot nozzles with needle nozzles for a more efficient exploitation of the lubricoolant.
- The volume flow of the extinguishing nozzles was adapted to demand using grindaix’s extinguishing nozzle technology.
- Bed flushing improved by Grindaix nozzle arrangement. Productivity increased by less use of lubricoolant.
* This is an exemplary application. This optimization is application-specific and not necessarily transferable to all machines of this type.
Der Ablauf einer Maschinenumrüstung
1 Coolant Audit
Analyse der Maschine/n vor Ort (ca. 5h /Maschine) im Produktionsbetrieb. Analyse der Verrohrungen im Maschinenraum – Maschine nur 1 h – offline. Erfassung Ihrer Einspar- und Optimierungspotenziale.
2 Engineering / Zusammenstellung des Umrüstsatzes
Darstellung Ihrer aktuellen KSS-Situation inkl. Potenzialen (€/kWh/[l/min]). Technische Empfehlung der Umbaumaßnahme inkl. Stückliste.
3 Umbau
Einbau des Grindaix Umrüstsatzes in Ihre Werkzeugmaschine inkl. aller mechanischen/mechatronischen Arbeiten CE-Konformität, Dokumentationsänderung, Haftung.
4 Inbetriebnahme
Prüfung Ihrer Verbesserungen im Hinblick auf Produktivität (Taktzeit), Werkzeugstandzeit, Energieverbrauch, KSS-Einsparung (Nachweis).